Berth Allocation

The shipping line or agent is to email the vessel's particulars, service lane, and vessel definition (general stowage plan, lashing arrangement plan, reefer arrangement plan, hatch securing, and container capacity table) to the ESCO Planner at least 1 week prior to calling. Vessels defined with CASP (Computer Automated Stowage Planning) are acceptable.

The shipping line or agent is to submit the long-term calling rotations 1 month prior to calling to the ESCO Planner in order to make a long-term vessel plan for container booking.

7, 3 and 1 day(s) prior to arrival, the shipping line or agent is to update both the ETA (Estimate Time of Arrival) and the estimated volume of discharging/loading in order to allow the ESCO Planner to confirm the POB and ETD (Estimate Time of Departure)